Re: Weekly Acme update
From: n.haddad@relexsolutions.example
To: lena.fischer@acme-org.example, priya.nair@acme-org.example
Cc: marco.rossi@relexsolutions.example, n.haddad@relexsolutions.example, tomas.lindholm@relexsolutions.example
Surrounding conversation
Hi All, Hereby the weekly update. Update 29-09-2025 (Week 40) 🔴 Risk Risk Still six weeks behind. Recovery depends on UAT throughput over October. Timeline Recovering. Six weeks behind, holding rather than slipping further. [Image removed by sender] Topics worked on last week 1. Defect fixed and verified (Phase 2 - Technical Implementation) 2. Solution consultant onboarded Topics planned for this week 1. UAT on produce and dairy (Phase 4 - Testing) 2. Prepare go/no-go for November Potential risk identified 🔴 Risk 1. Still six weeks behind. Recovery depends on UAT throughput over October. If there is anything else you'd like to see in these update emails, please don't hesitate to let us know. Kind regards, Best regards, Ana Duarte Project Manager Image +351 913 882 145 | UTC +01:00 ana.duarte@relexsolutions.example Rua do Ouro 42, 1100-063 Lisboa Connect with me Image Image Plan better. Sell more. Waste less relexsolutions.example Image LinkedInYouTube
Hi All, Hereby the weekly update. Update 15-09-2025 (Week 38) 🔴 Risk Risk Fresh Phase 2 six weeks behind. Two causes: Acme UAT resourcing, and a calculation defect producing negative quantities in test. Both being addressed. Timeline Six weeks behind on the fresh workstream. [Image removed by sender] Topics worked on last week 1. Escalation call held Friday 2. Approximation approach agreed internally (Phase 3 - Business Configuration) Topics planned for this week 1. Fix the negative quantity defect (Phase 2 - Technical Implementation) 2. Add a consultant to drive UAT (Phase 4 - Testing). Nadia is confirmed Potential risk identified 🔴 Risk 1. Fresh Phase 2 six weeks behind. Two causes: Acme UAT resourcing, and a calculation defect producing negative quantities in test. Both being addressed. If there is anything else you'd like to see in these update emails, please don't hesitate to let us know. Kind regards, Best regards, Ana Duarte Project Manager Image +351 913 882 145 | UTC +01:00 ana.duarte@relexsolutions.example Rua do Ouro 42, 1100-063 Lisboa Connect with me Image Image Plan better. Sell more. Waste less relexsolutions.example Image LinkedInYouTube
Hi All, Hereby the weekly update. Update 01-09-2025 (Week 36) 🟡Slight Delay Question Still open from four updates ago. We are now proceeding on an approximation unless we hear otherwise this week. Risk Shelf life unresolved. Proceeding on an approximation so the build is not blocked. Timeline Holding. [Image removed by sender] Topics worked on last week 1. Drafted an approximation approach for remaining shelf life (Phase 3 - Business Configuration) Topics planned for this week 1. Put shelf life on the escalation agenda 1. Begin UAT preparation (Phase 4 - Testing) Potential risk identified 🟡Slight Delay 1. Shelf life unresolved. Proceeding on an approximation so the build is not blocked. If there is anything else you'd like to see in these update emails, please don't hesitate to let us know. Kind regards, Best regards, Ana Duarte Project Manager Image +351 913 882 145 | UTC +01:00 ana.duarte@relexsolutions.example Rua do Ouro 42, 1100-063 Lisboa Connect with me Image Image Plan better. Sell more. Waste less relexsolutions.example Image LinkedInYouTube
Hi All, Sorry for the delay in the weekly update! Hereby the weekly update. Update 04-08-2025 (Week 32) 🟡Slight Delay Question We need remaining shelf life at the point of order, per article per site. MARA-MHDHB appears to be total shelf life rather than remaining. Is remaining life stored anywhere, and if not, is goods receipt date available outside the WMS? Risk Shelf life still unresolved. Acme warehouse team unavailable. Timeline Two weeks of float used. [Image removed by sender] Topics worked on last week 1. Configuration continues on the parts that do not need shelf life (Phase 3 - Business Configuration) Topics planned for this week 1. Escalate shelf life if no answer this week (Phase 2 - Technical Implementation) Potential risk identified 🟡Slight Delay 1. Shelf life still unresolved. Acme warehouse team unavailable. If there is anything else you'd like to see in these update emails, please don't hesitate to let us know. Kind regards, Best regards, Ana Duarte Project Manager Image +351 913 882 145 | UTC +01:00 ana.duarte@relexsolutions.example Rua do Ouro 42, 1100-063 Lisboa Connect with me Image Image Plan better. Sell more. Waste less relexsolutions.example Image LinkedInYouTube
Hi All, Hereby the weekly update. Update 21-07-2025 (Week 30) 🟡Slight Delay Question We need remaining shelf life at the point of order, per article per site. MARA-MHDHB appears to be total shelf life rather than remaining. Is remaining life stored anywhere, and if not, is goods receipt date available outside the WMS? Risk Shelf life field mapping unresolved for two weeks. Blocks the ordering logic. Timeline One week of float used. Not yet a concern. [Image removed by sender] Topics worked on last week 1. Produce and dairy configuration 60% complete (Phase 3 - Business Configuration) 2. Shelf life field mapping (Phase 2 - Technical Implementation) NOT FINISHED Topics planned for this week 1. Chase shelf life for the second time (Phase 2 - Technical Implementation) Potential risk identified 🟡Slight Delay 1. Shelf life field mapping unresolved for two weeks. Blocks the ordering logic. If there is anything else you'd like to see in these update emails, please don't hesitate to let us know. Kind regards, Best regards, Ana Duarte Project Manager Image +351 913 882 145 | UTC +01:00 ana.duarte@relexsolutions.example Rua do Ouro 42, 1100-063 Lisboa Connect with me Image Image Plan better. Sell more. Waste less relexsolutions.example Image LinkedInYouTube
Hi All, Hereby the weekly update. Update 07-07-2025 (Week 28) 🟢 On Track Timeline On track. [Image removed by sender] Topics worked on last week 1. Fresh category structure loaded for produce and dairy (Phase 3 - Business Configuration) 2. Shelf life request sent to Priya (Phase 2 - Technical Implementation) Topics planned for this week 1. Continue category configuration (Phase 3 - Business Configuration) 1. Await shelf life mapping (Phase 2 - Technical Implementation) If there is anything else you'd like to see in these update emails, please don't hesitate to let us know. Kind regards, Best regards, Ana Duarte Project Manager Image +351 913 882 145 | UTC +01:00 ana.duarte@relexsolutions.example Rua do Ouro 42, 1100-063 Lisboa Connect with me Image Image Plan better. Sell more. Waste less relexsolutions.example Image LinkedInYouTube