Hi Robert, Lena, Monthly steering report, January 2026. Status: 🟢 On Track Six weeks live. Stable. - No incidents over the holiday period. - Bakery workstream scoping with Meridian has begun. - Q1 measurement will be reported in April against the agreed baseline. [Image removed by sender] What we need from you: None. Marco Rossi Account Executive Image +351 912 447 026 | CET/CEST marco.rossi@relexsolutions.example Rua do Ouro 42, 1100-063 Lisboa Connect with me Image Image Plan better. Sell more. Waste less relexsolutions.example Image LinkedInYouTube Image

Surrounding conversation

Marco Rossi · Message 1 · 2026-04-10T17:40:00

Hi Robert, Lena, Monthly steering report, March 2026. Status: 🟢 On Track First full quarter of fresh live. Waste down from 4.1% to 3.4%. - Approximately 118 tonnes of fresh waste avoided across the 25 store cohort. - Approximately 296 tonnes CO2e avoided, on Acme's own published conversion factors. - Two caveats apply and are in the detail note. The figure should not be scaled to the full estate without discussion. - On the twelve month question: as Robert set out at the SOW review, this was always framed as an anticipation on our side rather than a commitment, and we have reported against it on that basis throughout. - Bakery build progressing. [Image removed by sender] What we need from you: None. Marco Rossi Account Executive Image +351 912 447 026 | CET/CEST marco.rossi@relexsolutions.example Rua do Ouro 42, 1100-063 Lisboa Connect with me Image Image Plan better. Sell more. Waste less relexsolutions.example Image LinkedInYouTube Image

Marco Rossi · Message 3 · 2025-11-28T17:00:00

Hi Robert, Lena, Monthly steering report, November 2025. Status: 🟢 On Track Replanned. Fresh go-live 15 December for three categories. - Go/no-go held 17 November. Produce, dairy and chilled approved. - Bakery descoped to a separate workstream starting March 2026. - This is two deliveries rather than three. Any plan document showing three waves is superseded. [Image removed by sender] What we need from you: None. Marco Rossi Account Executive Image +351 912 447 026 | CET/CEST marco.rossi@relexsolutions.example Rua do Ouro 42, 1100-063 Lisboa Connect with me Image Image Plan better. Sell more. Waste less relexsolutions.example Image LinkedInYouTube Image

Marco Rossi · Message 4 · 2025-10-31T16:20:00

Hi Robert, Lena, Monthly steering report, October 2025. Status: 🟡Slight Delay Two of the six weeks recovered. Go/no-go on track for 15 November. - UAT running on produce, dairy and chilled ready meals. - Bakery accuracy is poor and we expect to recommend descoping it. - Acme's fresh category manager is unavailable until mid November, which limits how fast UAT findings can be resolved. [Image removed by sender] What we need from you: Confirmation that a bakery descope is acceptable in principle. Marco Rossi Account Executive Image +351 912 447 026 | CET/CEST marco.rossi@relexsolutions.example Rua do Ouro 42, 1100-063 Lisboa Connect with me Image Image Plan better. Sell more. Waste less relexsolutions.example Image LinkedInYouTube Image

Marco Rossi · Message 5 · 2025-09-30T17:10:00

Hi Robert, Lena, Monthly steering report, September 2025. Status: 🔴 Risk Fresh Phase 2 is six weeks behind. Recovery plan in place. - Two causes: UAT resourcing on the Acme side, and a defect on ours. The defect is fixed. - RELEX has added a solution consultant for two weeks at our own cost. - A go or no-go decision is set for 15 November. [Image removed by sender] What we need from you: UAT capacity from the Acme side through October. Marco Rossi Account Executive Image +351 912 447 026 | CET/CEST marco.rossi@relexsolutions.example Rua do Ouro 42, 1100-063 Lisboa Connect with me Image Image Plan better. Sell more. Waste less relexsolutions.example Image LinkedInYouTube Image